NEW DELHI: State-owned NHPCBSE 0.25 % today said it has restored Unit-3 of Chutak power plant in Kargil district of Jammu and Kashmir on Tuesday.
“Unit 3 of Chutak Power Station in Jammu & Kashmir which was under complete shutdown due to problem in water parts has started generation on January 12, 2016,” NHPC Ltd said in a BSE filing today.
Earlier in November last year, the company has informed BSE that the Units 2 and 3 of the Chutak power station were completely shutdown due to certain technical reasons from October 25 and October 31, 2015 respectively.
In September, NHPC had said that Chutak power plant was completely restored on September 10, 2015.
The power facility is run-of-the-river scheme with an installed capacity of 44 mw (4X11 mw) and taps the Suru river in Kargil district.
Follow this link to join our WhatsApp group: Join Now
Be Part of Quality Journalism |
Quality journalism takes a lot of time, money and hard work to produce and despite all the hardships we still do it. Our reporters and editors are working overtime in Kashmir and beyond to cover what you care about, break big stories, and expose injustices that can change lives. Today more people are reading Kashmir Observer than ever, but only a handful are paying while advertising revenues are falling fast. |
ACT NOW |
MONTHLY | Rs 100 | |
YEARLY | Rs 1000 | |
LIFETIME | Rs 10000 | |