ISLAMABAD: The government on Thursday cleared the 969-megawatt Neelum Jhelum hydroelectric power project at a revised cost of Rs410 billion with a pinch of salt as the scheme, despite being plagued with mismanagement and corruption, must be executed because of its strategic nature.
The project was approved during the first government of Benazir Bhutto in 1989 with the cost standing at Rs15.3 billion. The cost was first revised in 2002 during the General Pervez Musharraf government before Pakistan Peoples Partys last government pushed the estimate to Rs274.9 billion in 2013.
The current PML-N government has further revised the cost upwards, expecting a capital injection of Rs410 billion.
Sending the project for final approval of the highest decision-making body, the Central Development Working Party (CDWP) also ordered a third-party assessment of the higher cost.
Headed by Planning and Development Minister Ahsan Iqbal, the CDWP also conditionally cleared two projects valuing Rs49.2 billion for the installation of smart electricity meters and billing systems in the jurisdictions of Lahore and Islamabad power distribution companies.
Talking to The Express Tribune, Iqbal said he cleared the projects depending on four conditions.
One of these is that the Ministry of Water and Power will provide a certificate that its recommended technology is tested, suitable and reliable as per local requirements. Furthermore, local bidders will be allowed to participate in the tender and the project cost will not be more than the cost of similar projects in other parts of the world.
Talking about the Neelum Jhelum project, Iqbal said against the proposed cost, the CDWP cut the estimate by Rs4 billion by lowering the contingency component to the standard 3%.
He said the main increase in the cost was on account of price escalation and exchange rate losses, but independent experts would verify these claims.
The CDWP will prepare a summary for Ecnec (Executive Committee of National Economic Council) to highlight poor management of the project, he said.
General (retired) Mohammad Zubair, who is the project CEO, has been accused of mismanagement.
India is building the Kishan Ganga project upstream and Pakistan has already lost its case in the International Court of Arbitration and will not be in a position to produce 969MW due to a reduced flow of water.
The Neelum Jhelum project will be completed at an exorbitant price of $4.23 million per megawatt the highest ever for any hydroelectric power project, according to project documents. The cost of under-construction Dasu hydroelectric power project is estimated at $2.25 million per megawatt while the Bunji project will cost $1.87 million.
At this price, the Neelum Jhelum projects generation cost per unit will be Rs11.17, resulting in a loss of Rs0.93 per unit from the first day after its commissioning. At the price of Rs274.9 billion, the project was supposed to generate electricity at a profit of Rs1.71 per unit.
The National Accountability Bureau has launched an inquiry into the conduct of Wapda and project management officials after allegations of kickbacks in procurement of Rs19.5 billion worth of tunnel-boring machines.
The machines were brought with the argument that the project would be completed one and a half year ahead of the planned commissioning in November 2016. So far, only 70% civil work has been completed.
The exchange rate losses have been estimated at Rs72.4 billion, but the Planning Commission termed this figure inflated on the basis of actual loss of only Rs2.5 billion against the 70% work completed.
Wapda has claimed an increase of Rs63 billion in the price, which again is highly inflated given the fact that so far actual escalation was Rs29 billion against 61% completed work.
The projects foreign loan requirement has also jumped from $328 million to roughly $1.9 billion.
Follow this link to join our WhatsApp group: Join Now
Be Part of Quality Journalism |
Quality journalism takes a lot of time, money and hard work to produce and despite all the hardships we still do it. Our reporters and editors are working overtime in Kashmir and beyond to cover what you care about, break big stories, and expose injustices that can change lives. Today more people are reading Kashmir Observer than ever, but only a handful are paying while advertising revenues are falling fast. |
ACT NOW |
MONTHLY | Rs 100 | |
YEARLY | Rs 1000 | |
LIFETIME | Rs 10000 | |